Bayswater-Bassendean Path commenced!
- gclark8
- Posts: 959
- Joined: Sat May 14, 2011 7:09 am
- Location: Bassendean, WA
Bayswater-Bassendean Path commenced!
Postby gclark8 » Sat Nov 12, 2011 12:32 pm
George.
-
- Posts: 840
- Joined: Thu Feb 26, 2009 1:16 pm
Re: Bayswater-Bassendean Path commenced!
Postby fixed » Sun Nov 13, 2011 3:48 pm
- wagr1213
- Posts: 128
- Joined: Sun Mar 28, 2010 1:24 pm
- Location: Beechboro
Re: Bayswater-Bassendean Path commenced!
Postby wagr1213 » Mon Nov 14, 2011 2:53 pm
PSP-Cyclists critique of the infrastructure
by wagr1213 » Tue Nov 08, 2011 11:58 pm
Work commenced today on construction of the extension of the PSP from Tonkin Hwy to Bassendean Station.
Im told that the route will swing away from where it currently becomes a section of grey black bitumen following the existing parallelling of the railway closer to the rail reserve down to the Kattaning st xing lights - after xing the intersection it will continue down the Guildford rd side of the rail corridor to the Collier rd crossing which has existing upgraded pedestrian/cycleway gates to enable changing to the western side of the railway.
Machines spent today cutting a route east through the grasses towards Ashfield station on the Guildford rd side.
Not before time!
- gclark8
- Posts: 959
- Joined: Sat May 14, 2011 7:09 am
- Location: Bassendean, WA
Re: Bayswater-Bassendean Path commenced!
Postby gclark8 » Mon Nov 14, 2011 6:36 pm
Bayswater end:
Reason: Images fixed
George.
- jet-ski
- Posts: 1404
- Joined: Thu Dec 06, 2007 5:51 pm
- Location: Perth WA
- Contact:
Re: Bayswater-Bassendean Path commenced!
Postby jet-ski » Mon Nov 14, 2011 7:12 pm
-
- Posts: 478
- Joined: Sat Jun 21, 2008 9:47 am
- Location: Ballajura, Western Australia
Re: Bayswater-Bassendean Path commenced!
Postby R12RT » Mon Nov 14, 2011 8:23 pm
I would have to agree that this stretch is less of a problem than Bassendean to Midland.
2010 Malvern Star Oppy C6
2014 Giant Propel Advanced 1
- gclark8
- Posts: 959
- Joined: Sat May 14, 2011 7:09 am
- Location: Bassendean, WA
Re: Bayswater-Bassendean Path commenced!
Postby gclark8 » Tue Nov 15, 2011 1:55 am
The Crossings will be the same as Caledonian Ave Maylands.R12RT wrote:What theory are going to do to make crossing Katanning St and Collier Rd will be interesting. These are very busy intersections.
Edit: check www.nearmap.com for an aerial view.
George.
-
- Posts: 478
- Joined: Sat Jun 21, 2008 9:47 am
- Location: Ballajura, Western Australia
Re: Bayswater-Bassendean Path commenced!
Postby R12RT » Tue Nov 15, 2011 9:40 am
That is what I would have expected.gclark8 wrote:The Crossings will be the same as Caledonian Ave Maylands.R12RT wrote:What theory are going to do to make crossing Katanning St and Collier Rd will be interesting. These are very busy intersections.
Although I am unsure what else could be done, these are going to be very dangerous intersections as they will be a lot busier than Caledonian Ave.
2010 Malvern Star Oppy C6
2014 Giant Propel Advanced 1
-
- Posts: 840
- Joined: Thu Feb 26, 2009 1:16 pm
Re: Bayswater-Bassendean Path commenced!
Postby fixed » Tue Nov 15, 2011 2:47 pm
Crossing Lord is going to be a stumbling point. The PSP should go under Lord St and via Success Hill Station go over the river along the rail line. At the rate the PSP is getting further east, I will be an old man before it reaches Midland.
- gclark8
- Posts: 959
- Joined: Sat May 14, 2011 7:09 am
- Location: Bassendean, WA
Re: Bayswater-Bassendean Path commenced!
Postby gclark8 » Tue Nov 15, 2011 4:19 pm
George.
- wagr1213
- Posts: 128
- Joined: Sun Mar 28, 2010 1:24 pm
- Location: Beechboro
Re: Bayswater-Bassendean Path commenced!
Postby wagr1213 » Thu Dec 22, 2011 1:23 am
R12RT wrote:That is what I would have expected.gclark8 wrote:The Crossings will be the same as Caledonian Ave Maylands.R12RT wrote:What theory are going to do to make crossing Katanning St and Collier Rd will be interesting. These are very busy intersections.
Although I am unsure what else could be done, these are going to be very dangerous intersections as they will be a lot busier than Caledonian Ave.
Well the PTA required fencework, Gates and associated culvert work is almost finished along this section now so at least some progress is being made.
Regarding the crossings - the same style of PSP crossing as the Caledonian Av arrangement has been employed at Hamilton Rd & Wharf St crossings on the Armadale line PSP
Both of these crossings are quite busy ( possibly much busier than Caledonian Av) and they seem to be working ok, though it has taken a little time for the tin box brigade to adapt to the need to keep the clearway "Clear" but it is improving - You will of course always get the occassional ignoramous that is totally oblivious to the clearway requirements who will block the path.
Not sure why similar requirements havnt been put in place at the Welshpool Rd crossing Now there is a crossing which is dangerous to traverse.
As with Caledonian Av, the onus is still on the Cyclist to give way to traffic movements when the flow of traffic is being controlled by the traffic lights, but when the gates are down, it should be just as sweet crossing Collier Rd and Kattanning St, as it is at Caledonian Av, Hamilton Rd & Wharf St and lets face it - I think we all try to be travelling thru the crossings when there is a train setting off the gates.
-
- Posts: 119
- Joined: Sat Jan 16, 2010 12:35 am
Re: Bayswater-Bassendean Path commenced!
Postby dampier » Fri Feb 10, 2012 1:51 pm
I went to Midland the other day and thought that there would be some visible progress on the path. Does anyone know when it will be started / finished?
-
- Posts: 86
- Joined: Tue Jun 28, 2011 12:12 pm
Re: Bayswater-Bassendean Path commenced!
Postby troyww » Sat Feb 11, 2012 3:36 pm
- CycleSnail
- Posts: 559
- Joined: Thu Feb 26, 2009 1:23 pm
- Location: Bassendean, WA
- Contact:
Re: Bayswater-Bassendean Path commenced!
Postby CycleSnail » Mon Feb 13, 2012 7:04 pm
"This financial year" is the answer I was given. A good time for the minister would be to open it during bike week, but that is clearly not going to happen at the rate they are progressing.dampier wrote:Hi,
I went to Midland the other day and thought that there would be some visible progress on the path. Does anyone know when it will be started / finished?
- Aushiker
- Posts: 22396
- Joined: Tue Jun 05, 2007 1:55 pm
- Location: Walyalup land
- Contact:
Re: Bayswater-Bassendean Path commenced!
Postby Aushiker » Wed Feb 29, 2012 12:34 pm
Aushiker.com
- wagr1213
- Posts: 128
- Joined: Sun Mar 28, 2010 1:24 pm
- Location: Beechboro
Re: Bayswater-Bassendean Path commenced!
Postby wagr1213 » Wed Mar 14, 2012 11:39 pm
-
- Posts: 86
- Joined: Tue Jun 28, 2011 12:12 pm
Re: Bayswater-Bassendean Path commenced!
Postby troyww » Mon Apr 30, 2012 4:24 pm
-
- Posts: 237
- Joined: Fri Jan 06, 2012 7:52 pm
Re: Bayswater-Bassendean Path commenced!
Postby J Quinton » Mon Apr 30, 2012 9:17 pm
-
- Posts: 275
- Joined: Mon Mar 14, 2011 7:26 pm
- Location: Perth, Western Australia
Re: Bayswater-Bassendean Path commenced!
Postby wexford » Mon Apr 30, 2012 10:41 pm
It was deep soft sand, I lasted about 10 metres. Some MTBer
- Red Rider
- Posts: 1024
- Joined: Sun Jan 23, 2011 5:44 pm
- Location: Perth
Re: Bayswater-Bassendean Path commenced!
Postby Red Rider » Fri May 18, 2012 10:59 am
Click to view full-sized image!
-
- Posts: 11
- Joined: Sat Apr 07, 2012 2:55 am
Re: Bayswater-Bassendean Path commenced!
Postby Gnor » Sun May 20, 2012 3:32 am
- CycleSnail
- Posts: 559
- Joined: Thu Feb 26, 2009 1:23 pm
- Location: Bassendean, WA
- Contact:
Re: Bayswater-Bassendean Path commenced!
Postby CycleSnail » Sun May 20, 2012 9:39 am
http://a1.sphotos.ak.fbcdn.net/hphotos- ... 2942_n.jpg
- hiflange
- Posts: 1938
- Joined: Tue May 05, 2009 9:27 pm
- Location: Perth
- Contact:
Re: Bayswater-Bassendean Path commenced!
Postby hiflange » Sun May 20, 2012 9:50 am
- CycleSnail
- Posts: 559
- Joined: Thu Feb 26, 2009 1:23 pm
- Location: Bassendean, WA
- Contact:
Re: Bayswater-Bassendean Path commenced!
Postby CycleSnail » Sun May 20, 2012 10:28 am
The upstream footpath is going to get a concrete deck instead of the rough timber. It will then become the "temporary" PSP route to Midland.RobertFrith wrote:Drove along Guildford Road yesterday, the path looks so good! The bridge into Guildford itself has quite a way to go though
- Red Rider
- Posts: 1024
- Joined: Sun Jan 23, 2011 5:44 pm
- Location: Perth
Re: Bayswater-Bassendean Path commenced!
Postby Red Rider » Sun May 20, 2012 4:21 pm
The path is looking like it'll turn out to be a beauty, well prepared, wide.
- General Australian Cycling Topics
- Info / announcements
- Buying a bike / parts
- General Cycling Discussion
- The Bike Shed
- Cycling Health
- Cycling Safety and Advocacy
- Women's Cycling
- Bike & Gear Reviews
- Cycling Trade
- Stolen Bikes
- Bicycle FAQs
- The Market Place
- Member to Member Bike and Gear Sales
- Want to Buy, Group Buy, Swap
- My Bikes or Gear Elsewhere
- Serious Biking
- Audax / Randonneuring
- Retro biking
- Commuting
- MTB
- Recumbents
- Fixed Gear/ Single Speed
- Track
- Electric Bicycles
- Cyclocross and Gravel Grinding
- Dragsters / Lowriders / Cruisers
- Children's Bikes
- Cargo Bikes and Utility Cycling
- Road Racing
- Road Biking
- Training
- Time Trial
- Triathlon
- International and National Tours and Events
- Cycle Touring
- Touring Australia
- Touring Overseas
- Touring Bikes and Equipment
- Australia
- Western Australia
- New South Wales
- Queensland
- South Australia
- Victoria
- ACT
- Tasmania
- Northern Territory
- Country & Regional
Who is online
Users browsing this forum: No registered users
- All times are UTC+10:00
- Top
- Delete cookies
About the Australian Cycling Forums
The Australian Cycling Forums is a welcoming community where you can ask questions and talk about the type of bikes and cycling topics you like.
Bicycles Network Australia
Forum Information
Connect with BNA
This website uses affiliate links to retail platforms including ebay, amazon, proviz and ribble.